Search results

  1. R

    Please advice re: "Operation Conflict"

    Yes I understand it. Actually the Action Message appeared because the user had done an action to erase the message. She changed the Release Date but didn't notice the First Operation Date. Thank you for your attention. Regards, Rosalie Helena PT. Matsushi ta Semiconductor Indonesia
  2. R

    Please advice re: "Operation Conflict"

    Thank you for the reply. I found the case like this: release date : 11/07/04, first op start 07/06/04. Regards, Rosalie
  3. R

    Please advice re: "Operation Conflict"

    Dear Peggers, After running 24.1 Recalculate Capacity Plan, the message appeared as follows: "Operation Conflict". What should we do? We tried to change Due Date or Release Date, but the message still existed. It seems our actions were not suitable. What are the impacts if we ignore that...
  4. R

    Work Order Close & Forecast MPS

    Thank you so very much for your comprehensive reply. It is helpfull and gives us important view mostly about direct and indirect demand. We decide input forecast as we will use BW >= 1 and FW >= 1 (not decided yet). Fyi, We produce semiconductor with CumLeadTime = 5 days. One of our...
  5. R

    Work Order Close & Forecast MPS

    Thank you very much for your reply. It is helpfull. I tried the test as your suggetion and found that the oustanding quantity is not counted by MRP as supply so that MRP still give Release Order. Can you give a view how if we entry forecast as SO only? Our Forecast consumption: Forward 0...
  6. R

    Work Order Close & Forecast MPS

    Dear peggers, We are going to run MPS in eB2 version (Windows 2000). We produce Semiconductors and start to use eB2 April 2004. I have two questions. Please answer them :). About Outstanding WO (Work Order). Case: User has receipt WO less than Order Quantity and then Closed the WO. Does the...
Top