Syteline ERP 6.00.10 MRP re-plan of orders in arrears

Amethyst28

New Member
There is a known issue with the system that we use and I would like to understand if it's standard Syteline behavior or not. When MRP runs it does not recalculate the need by dates for orders with due dates in arrears. There has been a work around in place for years which is essentially every month everyone manually changing the purchase order due date to a point in the future. This is painful and messes with OTD metrics. So I guess I have two questions:

1. Is this normal?
2. Is there a systematic fix?
 