Version MFG/Pro eB
I set up a work center with 9 machines and 1 op/mach. The work center capacity for 2 shifts is 9 x 16hrs = 144.
I have a work order with order date and release date = today while due date = tomorrow. The total operation run time to produce the order qty (based on the routing) is 126.
I run 24.1 then check Work center Load summary. The 1st operation was scheduled to start a day before the due date while the rest of the operation was scheduled on the due date. The work center can accomodate the order qty in just 1 day, why does CRP do back schedule?
I set up a work center with 9 machines and 1 op/mach. The work center capacity for 2 shifts is 9 x 16hrs = 144.
I have a work order with order date and release date = today while due date = tomorrow. The total operation run time to produce the order qty (based on the routing) is 126.
I run 24.1 then check Work center Load summary. The 1st operation was scheduled to start a day before the due date while the rest of the operation was scheduled on the due date. The work center can accomodate the order qty in just 1 day, why does CRP do back schedule?