end effective BOM date considerted by MRP

aviovda

New Member
Hello

i have an mrp recommendation to produce 5 pcs of product "A"
due to today.

the problem
product "A" bom as of today, does not include
part "B" as a component, despite this, the mrp system creates demands for part B that`s may be because it considers the lead time of part A witch is 20 days (at that time there was a valid connection
between A and b).

MY question

how can i enforce the system to create
demands for planned work order without taking the lead time
factor into consideration .

thank you very much.
 