Alternate BOM's

HISTOGRAM

Member
Hi All,

Our production planner has asked an interesting question.

We have recently installed a new production line (we make fruit juice) as an expansion to an existing line. The new line utilises some new technologies which means that it uses slightly different packaging materials than the existing line.

So the question is can MFG run alternate BOM's at the same time? i.e. The 2 lines need to produce an article with the same parent item but utilising different components.

If you need any further help please ask.

Thanks in advance.
 
Hi
You can have as many BOMs in the system as you wish. The main one (used most often) will be defined in Item Planning maintenance and used for costng and planning purposes. When the work order is created, the system will take the default from there (Item master). Before releasing the WO, the operator can change the WO bom code to any other existing BOM. When the wo is released, the system will use this BOM code to build wo details. After the wo is released, the operator can change the actual WO bom by going to WO BOM maintenance.
Hope it helps

____________________________________
Max Viskov, max.viskov@32soft.com
Senior Consultant, Implementation Services
MFG/PRO Toronto User Group Board Member
32Soft Inc., an Official QAD Subcontractor